Feature flag controls
Access
To be able to turn on/off features behind feature flags in any of the
GitLab Inc. provided environments such as staging and production, you need to
have access to the ChatOps bot. The ChatOps bot
is currently running on the ops instance, which is different from
GitLab.com or dev.gitlab.org
.
Follow the ChatOps document to request access.
After you are added to the project test if your access propagated, run:
/chatops run feature --help
Rolling out changes
When the changes are deployed to the environments it is time to start rolling out the feature to our users. The exact procedure of rolling out a change is unspecified, as this can vary from change to change. However, in general we recommend rolling out changes incrementally, instead of enabling them for everybody right away. We also recommend you to not enable a feature before the code is being deployed. This allows you to separate rolling out a feature from a deploy, making it easier to measure the impact of both separately.
The GitLab feature library (using Flipper, and covered in the Feature Flags process guide) supports rolling out changes to a percentage of time to users. This in turn can be controlled using GitLab ChatOps.
For an up to date list of feature flag commands please see
the source code.
Note that all the examples in that file must be preceded by
/chatops run
.
If you get an error "Whoops! This action is not allowed. This incident will be reported." that means your Slack account is not allowed to change feature flags or you do not have access.
Enabling a feature for pre-production testing
As a first step in a feature rollout, you should enable the feature on
about.staging.gitlab.com
and dev.gitlab.org
.
These two environments have different scopes.
dev.gitlab.org
is a production CE environment that has internal GitLab Inc.
traffic and is used for some development and other related work.
staging.gitlab.com
has a smaller subset of GitLab.com database and repositories
and does not have regular traffic. Staging is an EE instance and can give you
a (very) rough estimate of how your feature will look and behave on GitLab.com.
Both of these instances are connected to Sentry so make sure you check the projects
there for any exceptions while testing your feature after enabling the feature flag.
For these pre-production environments, the commands should be run in a
Slack channel for the stage the feature is relevant to. For example, use the
#s_monitor
channel for features developed by the Monitor stage, Health
group.
To enable a feature for 25% of the time, run the following in Slack:
/chatops run feature set new_navigation_bar 25 --dev
/chatops run feature set new_navigation_bar 25 --staging
Enabling a feature for GitLab.com
When a feature has successfully been enabled on a pre-production environment and verified as safe and working, you can roll out the change to GitLab.com (production).
Communicate the change
Some feature flag changes on GitLab.com should be communicated with parts of the company. The developer responsible needs to determine whether this is necessary and the appropriate level of communication. This depends on the feature and what sort of impact it might have.
Guidelines:
- Consider notifying
#support_gitlab-com
beforehand. So in case if the feature has any side effects on user experience, they can mitigate and disable the feature flag to reduce some impact. - If the feature meets the requirements for creating a Change Management issue, create a Change Management issue per criticality guidelines.
- For simple, low-risk, easily reverted features, proceed and enable the feature in
#production
.
Process
When enabling a feature flag rollout, the system will automatically block the
ChatOps command from succeeding if there are active "severity::1"
or ~"severity::2"
incidents or in-progress change issues, for example:
/chatops run feature set gitaly_lfs_pointers_pipeline true
- Production checks fail!
- active incidents
2021-06-29 Canary deployment failing QA tests
The following /chatops
commands should be performed in the Slack
#production
channel.
When you begin to enable the feature, please link to the relevant
Feature Flag Rollout Issue within a Slack thread of the first /chatops
command you make so people can understand the change if they need to.
To enable a feature for 25% of the time, run the following in Slack:
/chatops run feature set new_navigation_bar 25
This sets a feature flag to true
based on the following formula:
feature_flag_state = rand < (25 / 100.0)
This will enable the feature for GitLab.com, with new_navigation_bar
being the
name of the feature.
This command does not enable the feature for 25% of the total users.
Instead, when the feature is checked with enabled?
, it will return true
25% of the time.
To enable a feature for 25% of actors such as users, projects, or groups, run the following in Slack:
/chatops run feature set some_feature 25 --actors
This sets a feature flag to true
based on the following formula:
feature_flag_state = Zlib.crc32("some_feature<Actor>:#{actor.id}") % (100 * 1_000) < 25 * 1_000
# where <Actor>: is a `User`, `Group`, `Project` and actor is an instance
During development, based on the nature of the feature, an actor choice should be made.
For user focused features:
Feature.enabled?(:feature_cool_avatars, current_user)
For group or namespace level features:
Feature.enabled?(:feature_cooler_groups, group)
For project level features:
Feature.enabled?(:feature_ice_cold_projects, project)
If you are not certain what percentages to use, simply use the following steps:
- 25%
- 50%
- 75%
- 100%
Between every step you'll want to wait a little while and monitor the appropriate graphs on https://dashboards.gitlab.net. The exact time to wait may differ. For some features a few minutes is enough, while for others you may want to wait several hours or even days. This is entirely up to you, just make sure it is clearly communicated to your team, and the Production team if you anticipate any potential problems.
Feature gates can also be actor based, for example a feature could first be
enabled for only the gitlab
project. The project is passed by supplying a
--project
flag:
/chatops run feature set --project=gitlab-org/gitlab some_feature true
For groups the --group
flag is available:
/chatops run feature set --group=gitlab-org some_feature true
Note that actor-based gates are applied before percentages. For example, considering the
group/project
as gitlab-org/gitlab
and a given example feature as some_feature
, if
you run these 2 commands:
/chatops run feature set --project=gitlab-org/gitlab some_feature true
/chatops run feature set some_feature 25 --actors
Then some_feature
will be enabled for both 25% of actors and always when interacting with
gitlab-org/gitlab
. This is a good idea if the feature flag development makes use of group
actors.
Feature.enabled?(:some_feature, group)
Lastly, to verify that the feature is deemed stable in as many cases as possible, you should fully roll out the feature by enabling the flag globally by running:
/chatops run feature set some_feature true
This changes the feature flag state to be enabled always, which overrides the
existing gates (for example, --group=gitlab-org
) in the above processes.
Note, that if an actor based feature gate is present, switching the
default_enabled
attribute of the YAML definition from false
to true
will not have any effect. The feature gate must be deleted first.
For example, a feature flag is set via ChatOps:
/chatops run feature set --project=gitlab-org/gitlab some_feature true
When the default_enabled
attribute in the YAML definition is switched to
true
, the feature gate must be deleted to have the desired effect:
/chatops run feature delete some_feature
Percentage of actors vs percentage of time rollouts
If you want to make sure a feature is always on or off for users, use a Percentage of actors rollout. Avoid using percentage of time rollouts in this case.
A percentage of time rollout can introduce inconsistent behavior when Feature.enabled?
is used multiple times in the code because the feature flag value is randomized each time
Feature.enabled?
is called on your code path.
Disabling feature flags
To disable a feature flag that has been globally enabled you can run:
/chatops run feature set some_feature false
To disable a feature flag that has been enabled for a specific project you can run:
/chatops run feature set --group=gitlab-org some_feature false
You cannot selectively disable feature flags for a specific project/group/user without applying a specific method of implementing the feature flags.
If a feature flag is disabled via ChatOps, that will take precedence over the default_enabled
value in the YML. In other words, you could have a feature enabled for on-premise installations but not for GitLab.com.
Feature flag change logging
ChatOps level
Any feature flag change that affects GitLab.com (production) via ChatOps is automatically logged in an issue.
The issue is created in the gl-infra/feature-flag-log project, and it will at minimum log the Slack handle of person enabling a feature flag, the time, and the name of the flag being changed.
The issue is then also posted to the GitLab internal Grafana dashboard as an annotation marker to make the change even more visible.
Changes to the issue format can be submitted in the ChatOps project.
Instance level
Any feature flag change that affects any GitLab instance is automatically logged in features_json.log. You can search the change history in Kibana. You can also access the feature flag change history for GitLab.com in Kibana.
Cleaning up
A feature flag should be removed as soon as it is no longer needed. Each additional feature flag in the codebase increases the complexity of the application and reduces confidence in our testing suite covering all possible combinations. Additionally, a feature flag overwritten in some of the environments can result in undefined and untested system behavior.
development
type feature flags should have a short life-cycle because their purpose
is for rolling out a persistent change. development
feature flags that are older
than 2 milestones are reported to engineering managers. The
report tool runs on a
monthly basis. For example, see the report for December 2021.
If a development
feature flag is still present in the codebase after 6 months we should
take one of the following actions:
- Enable the feature flag by default and remove it.
- Convert it to an instance, group, or project setting.
- Revert the changes if it's still disabled and not needed anymore.
To remove a feature flag, open one merge request to make the changes. In the MR:
- Add the ~"feature flag" label so release managers are aware the changes are hidden behind a feature flag.
- If the merge request has to be picked into a stable branch, add the
appropriate
~"Pick into X.Y"
label, for example~"Pick into 13.0"
. See the feature flag process for further details. - Remove all references to the feature flag from the codebase, including tests.
- Remove the YAML definition for the feature from the repository.
Once the above MR has been merged, you should:
- Clean up the feature flag from all environments with
/chatops run feature delete some_feature
. - Close the rollout issue for the feature flag after the feature flag is removed from the codebase.
Cleanup ChatOps
When a feature gate has been removed from the codebase, the feature record still exists in the database that the flag was deployed too. The record can be deleted once the MR is deployed to each environment:
/chatops run feature delete some_feature --dev
/chatops run feature delete some_feature --staging
Then, you can delete it from production after the MR is deployed to prod:
/chatops run feature delete some_feature