# Roadmap **[ULTIMATE]**
|
||
|
|
||
|
> Introduced in [GitLab Ultimate](https://about.gitlab.com/pricing) 10.5.
|
||
|
|
||
|
An Epic within a group containing **Start date** and/or **Due date**
|
||
|
can be visualized in a form of a timeline (e.g. a Gantt chart). The Epics Roadmap page
|
||
|
shows such a visualization for all the epics which are under a group and/or its subgroups.
|
||
|
|
||
|
![roadmap view](img/roadmap_view.png)
|
||
|
|
||
|
A dropdown allows you to show only open or closed epics. By default, all epics are shown.
|
||
|
|
||
|
![epics state dropdown](img/epics_state_dropdown.png)
|
||
|
|
||
|
Epics in the view can be sorted by:
|
||
|
|
||
|
- **Created date**
|
||
|
- **Last updated**
|
||
|
- **Start date**
|
||
|
- **Due date**
|
||
|
|
||
|
Each option contains a button that can toggle the order between **ascending** and **descending**. The sort option and order will be persisted to be used wherever epics are browsed including the [epics list view](../epics/index.md).
|
||
|
|
||
|
Roadmaps can also be [visualized inside an epic](../epics/index.md#roadmap-in-epics).
|
||
|
|
||
|
## Timeline duration
|
||
|
|
||
|
Starting with [GitLab Ultimate][ee] 11.0, Roadmap supports three different date ranges; Quarters, Months (Default) and Weeks.
|
||
|
|
||
|
### Quarters
|
||
|
|
||
|
![roadmap date range in quarters](img/roadmap_timeline_quarters.png)
|
||
|
|
||
|
In _Quarters_ preset, roadmap shows epics which have start or due dates _falling within_ or
|
||
|
_going through_ **past quarter**, **current quarter** and **next 4 quarters**, where _today_
|
||
|
is shown by the vertical red line in the timeline. The sub-headers underneath the quarter name on
|
||
|
the timeline header represent the month of the quarter.
|
||
|
|
||
|
### Months
|
||
|
|
||
|
![roadmap date range in months](img/roadmap_timeline_months.png)
|
||
|
|
||
|
In _Months_ preset, roadmap shows epics which have start or due dates _falling within_ or
|
||
|
_going through_ **past month**, **current month** and **next 5 months**, where _today_
|
||
|
is shown by the vertical red line in the timeline. The sub-headers underneath the month name on
|
||
|
the timeline header represent the date on starting day (Sunday) of the week. This preset is
|
||
|
selected by default.
|
||
|
|
||
|
### Weeks
|
||
|
|
||
|
![roadmap date range in weeks](img/roadmap_timeline_weeks.png)
|
||
|
|
||
|
In _Weeks_ preset, roadmap shows epics which have start or due dates _falling within_ or
|
||
|
_going through_ **past week**, **current week** and **next 4 weeks**, where _today_
|
||
|
is shown by the vertical red line in the timeline. The sub-headers underneath the week name on
|
||
|
the timeline header represent the days of the week.
|
||
|
|
||
|
## Timeline bar for an epic
|
||
|
|
||
|
The timeline bar indicates the approximate position of an epic based on its start
|
||
|
and due date. If an epic doesn't have a due date, the timeline bar fades
|
||
|
away towards the future. Similarly, if an epic doesn't have a start date, the
|
||
|
timeline bar becomes more visible as it approaches the epic's due date on the
|
||
|
timeline.
|