> - [Introduced](https://gitlab.com/gitlab-org/gitlab/merge_requests/1540) in [GitLab Starter](https://about.gitlab.com/pricing/) 9.1 for project milestones.
> - [Introduced](https://gitlab.com/gitlab-org/gitlab/merge_requests/5354) in [GitLab Premium](https://about.gitlab.com/pricing/) 10.8 for group milestones.
> - [Added](https://gitlab.com/gitlab-org/gitlab/merge_requests/6495) to [GitLab Starter](https://about.gitlab.com/pricing/) 11.2 for group milestones.
You're able to [promote project](index.md#promoting-project-milestones-to-group-milestones) to group milestones and still see the **Burndown Chart** for them, respecting license limitations.
The chart indicates the project's progress throughout that milestone (for issues assigned to it).
In particular, it shows how many issues were or are still open for a given day in the
milestone's corresponding period.
The Burndown Chart tracks when issues were created and when they were last closed—not their full history. For each day, it takes the number of issues still open and issues created that day and subtracts the number of issues closed that day.
**Issues that were created and assigned a milestone before its start date—and remain open as of the start date—are considered as having been opened on the start date**. Therefore, when the milestone start date is changed the number of opened issues on each day may change.
Reopened issues are
considered as having been opened on the day after they were last closed.
The Burndown Chart can also be toggled to display the cumulative open issue
weight for a given day. When using this feature, make sure issue weights have
been properly assigned, since an open issue with no weight adds zero to the